The Government has set a target of installing 60 GW of wind power capacity by 2022, against which 35 GW capacity has already been installed. The state wise installed capacity and energy generation (actual production) of wind power in the country during last three years and current year are given in Annexure -I.
The Government is promoting wind power projects in entire country by providing various fiscal and financial incentives such as Accelerated Depreciation benefit; concessional custom duty exemption on certain components of wind electric generators. Besides, Generation Based Incentive (GBI) is being provided to the wind projects commissioned before 31 March 2017.
In addition to fiscal and other incentives as stated above, following steps also have been taken to promote installation of wind capacity in the country:
- Technical support including wind resource assessment and identification of potential sites through the National Institute of Wind Energy, Chennai.
- In order to facilitate inter-state sale of wind power, the inter-state transmission charges and losses have been waived off for wind and solar projects to be commissioned by March, 2022.
- Issued Guidelines for Tariff Based Competitive Bidding Process for procurement of Power from Grid Connected Wind Power Projects. These Guidelines aim to enable the Distribution Licensees to procure wind power at competitive rates in a cost effective manner.
This was informed by Minister of State (I/C) for New and Renewable Energy and Power Shri R. K Singh in a written reply in the Lok Sabha today.
Annexure-I
State-wise installed capacity and energy generation of Wind Power
State | 2015-16 | 2016-17 | 2017-18 | 2018-19 | ||||
Installed Capacity (MW) | Energy Generation (MU) | Installed Capacity (MW) | Energy Generation (MU) | Installed Capacity (MW) | Energy Generation (MU) | Installed Capacity (MW) (as
on 30.11.20 18) |
Energy Generati on (MU) (as on 31.10.20
18) |
|
Andhra Pradesh | 400.10 | 2013.04 | 2187.45 | 3187.85 | 348.10 | 6354.11 | 107.40 | 774.50 |
Gujarat | 392.40 | 6446.58 | 1392.00 | 7720.01 | 272.80 | 9635.65 | 239.25 | 1885.09 |
Karnataka | 230.90 | 4797.95 | 882.30 | 6058.65 | 857.00 | 7410.29 | 63.90 | 998.60 |
Kerala | 8.40 | 51.45 | 8.00 | 72.59 | 1.00 | 98.46 | 0.00 | 10.78 |
Madhya Pradesh | 1261.40 | 1558.43 | 356.70 | 3563.17 | 22.10 | 4139.84 | 0.00 | 1081.38 |
Maharashtra | 207.85 | 6121.34 | 117.55 | 7490.75 | 12.60 | 6541.35 | 4.20 | 1060.68 |
Rajasthan | 685.50 | 4583.59 | 287.70 | 5562.52 | 16.00 | 5665.45 | 2.00 | 1123.47 |
Tamil Nadu | 158.80 | 7273.23 | 247.57 | 11935.26 | 335.64 | 12358.01 | 427.80 | 723.82 |
Telangana | 77.70 | 0.00 | 23.10 | 211.93 | 0.00 | 195.29 | 27.30 | 29.81 |
Others | 0.00 | 183.77 | 0.00 | 201.61 | 0.00 | 267.65 | 0.00 | 75.70 |
Total | 3423.05 | 33029.38 | 5502.37 | 46004.34 | 1865.24 | 52666.1 | 871.85 | 7763.83 |
Cumulative
Capacity |
26777.39 | — | 32279.76 | – | 34145.00 | – | 35016.85 | – |
Annexure-II
SECI Bid | Project Capacity (MW) | Project Locations | Tariff Rs./unit | Present Status |
SECI
Tranche I |
1049.90 | Thirunelveli (Tamil Nadu) and Bhuj & Bachau (Gujarat) | 3.46 | 425.9 MW commissioned. Financial closure achieved for 624 MW |
SECI
Tranche II |
1000 | Tuticorin (Tamil Nadu) and Bhuj & Bachau (Gujarat) | 2.65-2.65 | Scheduled commissioning date is 03.05.2019 |
SECI
Tranche III |
2000 | Tuticorin (Tamil Nadu) and Bhuj & Bachau (Gujarat) | 2.44-2.45 | Scheduled commissioning date is 23.11.2019 |
SECI
Tranche IV |
2000 | Pugalur, Thirunelveli, & Palakkad (Tamil Nadu) and Bhuj (Gujarat) | 2.51-2.52 | Scheduled commissioning date is 28.02.2020 |
SECI
Tranche V |
1190 | Bhuj (Gujarat) and Hiryur (Karnataka) | 2.76-2.77 | Scheduled commissioning date is 22.07.2020 |
NTPC | 1150 | Pavagada (Andhra Pradesh), Osmanabad (Maharashtra), Karur & Tirupur (Tamil Nadu), Kutch (Gujarat) and Devangere (Karnataka) | 2.77-2.83 | Scheduled commissioning date is 13.07.2020 |
Total | 8389.9 |